Tuesday, December 16th 2014, 5:52 pm
The government has amended its lawsuit against the wind farm that's under construction in Osage County.
The government filed suit on behalf of the Osage Nation.
11/21/2014 Related Story: Lawsuit Claims Osage Wind Project Is Breaking The Law
It's no longer trying to stop the construction because the work is too far along. Now it's focusing on the land's mineral rights.
The government claims the groups behind the wind farm didn't get the right approval and leases from the Secretary of the Interior.
The lawsuit also claims the group used minerals it dug up to build the turbines' foundations.
11/21/2014 Related Story: Company Behind Osage Wind Project, 'Benefits Are Far-Reaching'
December 16th, 2014
September 29th, 2024
September 17th, 2024
November 21st, 2024
November 21st, 2024
November 21st, 2024