Thursday, March 8th 2018, 11:41 am
A project to resurface Highway 169 between Collinsville and Owasso will start April 20th.
The Oklahoma Transportation Commission awarded a contract for the work early last month.
The Oklahoma Department of Transportation says Diamond Surface, Inc. from Rogers, Minnesota won the $2,006,703.55 contract for the work.
ODOT says the work will resurface 3.4 miles of Highway 169, from just south of the 116th Street North intersection north to 146th Street North near Collinsville.
That part of the highway was built in the early 1990s and some of the concrete has deteriorated significantly since then.
The contract stipulates three types of repairs to the concrete: replacing the full depth of the concrete for any sections that need it, full depth patching of joints where needed, and installing dowel pins between sections of concrete. The contract says the full depth replacement of concrete sections will be the 1st priority and that every joint will be fixed by one of the options.
The contract gives the contractor 90 calendar days to complete the work. Traffic will be narrowed to one lane during the work. The contract includes fixing the pavement on the southbound 169 exit ramp to 116th Street North and the southbound entrance ramp to 169 from 116th Street North.
It says neither ramp can be closed for more than seven consecutive days and they can't be closed at the same time.
March 8th, 2018
September 29th, 2024
September 17th, 2024
November 4th, 2024
November 4th, 2024
November 4th, 2024
November 4th, 2024